Roadmap:GIPL: Difference between revisions

From CSDMS
m (Fix link to build notes)
No edit summary
Line 32: Line 32:


| IRF interface done by    = Elchin Jafarov
| IRF interface done by    = Elchin Jafarov
| IRF interface status      = Pending
| IRF interface status      = Done
| IRF interface link        = None
| IRF interface link        = None
| IRF interface finished by = mm/dd/yyyy
| IRF interface finished by = 08/12/2011


| CCA component done by    = Name
| CCA component done by    = Jisamma Kallumadikal
| CCA component status      = Pending
| CCA component status      = Done
| CCA component link        = None
| CCA component link        = None
| CCA component finished by = mm/dd/yyyy
| CCA component finished by = 08/12/2011


| build GUI done by        = Name
| build GUI done by        = Elchin Jafarov
| build GUI status          = Pending
| build GUI status          = Pending
| build GUI link            = None
| build GUI link            = None
| build GUI finished by    = mm/dd/yyyy
| build GUI finished by    = 08/15/2011


| template input done by      = Name
| template input done by      = Elchin Jafarov
| template input status      = Pending
| template input status      = Done
| template input link        = None
| template input link        = None
| template input finished by  = mm/dd/yyyy
| template input finished by  = 08/15/20111


| stand alone documentation done by    = Name
| stand alone documentation done by    = Name

Revision as of 16:50, 15 August 2011


Roadmap GIPL component status:

Project owner CSMDS-IF: Elchin Jafarov
Start date project: 08/11/2011
Estimated release date: 08/11/2012
Project status: 40%

Milestone: Executable

75%

Status Task Task owner Information Estimated completion date
Provide metadata Elchin Jafarov More... 08/11/2011
Upload source Elchin Jafarov More... 08/12/2011
Upload input and output data Elchin Jafarov mm/dd/yyyy
Compile Elchin Jafarov More... 08/12/2011


Milestone: Standalone component

42%

Status Task Task owner Information Estimated completion date
IRF interface Elchin Jafarov 08/12/2011
Create CCA component Jisamma Kallumadikal 08/12/2011
Build GUI Elchin Jafarov 08/15/2011
Template input file Elchin Jafarov 08/15/20111
Documentation TBD mm/dd/yyyy
Sample BLD files TBD mm/dd/yyyy
Testing TBD mm/dd/yyyy


Milestone: Coupled component

0%

Status Task Task owner Information Estimated completion date
Getter/setter Interface TBD mm/dd/yyyy
Documentation TBD mm/dd/yyyy
Sample BLD files TBD mm/dd/yyyy
Testing TBD mm/dd/yyyy