Roadmap:LTRANS: Difference between revisions

From CSDMS
No edit summary
No edit summary
Line 10: Line 10:
| project owner email      = jisamma.kallumadikal@colorado.edu
| project owner email      = jisamma.kallumadikal@colorado.edu
| project owner start date  = 07/01/2011
| project owner start date  = 07/01/2011
| project estimated finish date = 10/01/2011
| project estimated finish date = 31/01/2012


| questionnaire fill out by = Name
| questionnaire fill out by = Name

Revision as of 14:46, 12 January 2012


Roadmap LTRANS component status:

Project owner CSMDS-IF: Jisamma Kallumadikal
Start date project: 07/01/2011
Estimated release date: 31/01/2012
Project status: 40%

Milestone: Executable

100%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png Provide metadata TBD More... mm/dd/yyyy
Checkbox-ok-32.png Upload source Jisamma Kallumadikal [none More...] 09/13/2011
Checkbox-ok-32.png Upload input and output data Jisamma Kallumadikal mm/dd/yyyy
Checkbox-ok-32.png Compile Jisamma Kallumadikal 09/12/2011


Milestone: Standalone component

14%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png IRF interface Zack Schlag 09/07/2011
Checkbox-32.png Create CCA component Jisamma Kallumadikal mm/dd/yyyy
Checkbox-32.png Build GUI TBD mm/dd/yyyy
Checkbox-32.png Template input file TBD mm/dd/yyyy
Checkbox-32.png Documentation TBD mm/dd/yyyy
Checkbox-32.png Sample BLD files TBD mm/dd/yyyy
Checkbox-32.png Testing TBD mm/dd/yyyy


Milestone: Coupled component

0%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png Getter/setter Interface Jisamma Kallumadikal 09/09/2011
Checkbox-32.png Documentation TBD mm/dd/yyyy
Checkbox-32.png Sample BLD files TBD mm/dd/yyyy
Checkbox-32.png Testing TBD mm/dd/yyyy