Roadmap:LTRANS: Difference between revisions

From CSDMS
No edit summary
No edit summary
Line 66: Line 66:
| stand alone testing finished by      = mm/dd/yyyy
| stand alone testing finished by      = mm/dd/yyyy


| getters-setters done by    = Name
| getters-setters done by    = Jisamma Kallumadikal
| getters-setters status      = Pending
| getters-setters status      = Done
| getters-setters link        = None
| getters-setters link        = None
| getters-setters finished by = mm/dd/yyyy
| getters-setters finished by = 09/09/2011


| coupled documentation done by    = Name
| coupled documentation done by    = Name

Revision as of 10:34, 13 September 2011


Roadmap LTRANS component status:

Project owner CSMDS-IF: Jisamma Kallumadikal
Start date project: 07/01/2011
Estimated release date: 10/01/2011
Project status: 40%

Milestone: Executable

100%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png Provide metadata TBD More... mm/dd/yyyy
Checkbox-ok-32.png Upload source Jisamma Kallumadikal [none More...] 09/13/2011
Checkbox-ok-32.png Upload input and output data Jisamma Kallumadikal mm/dd/yyyy
Checkbox-ok-32.png Compile Jisamma Kallumadikal 09/12/2011


Milestone: Standalone component

14%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png IRF interface Zack Schlag 09/07/2011
Checkbox-32.png Create CCA component Jisamma Kallumadikal mm/dd/yyyy
Checkbox-32.png Build GUI TBD mm/dd/yyyy
Checkbox-32.png Template input file TBD mm/dd/yyyy
Checkbox-32.png Documentation TBD mm/dd/yyyy
Checkbox-32.png Sample BLD files TBD mm/dd/yyyy
Checkbox-32.png Testing TBD mm/dd/yyyy


Milestone: Coupled component

0%

Status Task Task owner Information Estimated completion date
Checkbox-ok-32.png Getter/setter Interface Jisamma Kallumadikal 09/09/2011
Checkbox-32.png Documentation TBD mm/dd/yyyy
Checkbox-32.png Sample BLD files TBD mm/dd/yyyy
Checkbox-32.png Testing TBD mm/dd/yyyy